| BID PROPOSAL WORKSHEET | |||||
| GREEN AVE IMPROVEMENTS | |||||
| JANUARY 2008 | |||||
| Item | DESCRIPTION | APPROX. | UNIT | ITEM | |
| No. | QTY. | UNIT | PRICE | TOTAL | |
| 1 | MAINTENANCE AND PROTECTION OF TRAFFIC | 100% | LS | ||
| Write Unit Price and Item Total : | |||||
| 2 | POLICE TRAFFIC DIRECTORS | 120 | MAN HRS | $65.00 | |
| Write Unit Price and Item Total : | |||||
| 3 | SUPERPAVE SURFACE COURSE | 1350 | TONS | ||
| Write Unit Price and Item Total : | |||||
| 4 | BITUMINOUS STABILIZED BASE, MIX I-2 | 350 | TONS | ||
| Write Unit Price and Item Total : | |||||
| 5 | DENSE GRADED AGGREGATE BASE COURSE (6"th.) | 600 | C.Y. | ||
| Write Unit Price and Item Total : | |||||
| 6 | MILLING, PROFILE 0" TO 1.5" | 7,300 | S.Y. | ||
| Write Unit Price and Item Total : | |||||
| 7 | ROOF DRAINS, (SDR 35) | 200 | L.F. | ||
| Write Unit Price and Item Total : | |||||
| 8 | RESET MANHOLE CASTING | 25 | EACH | ||
| Write Unit Price and Item Total : | |||||
| 9 | RESET / REPLACE VALVE STEM / RISER | 55 | EACH | ||
| Write Unit Price and Item Total : | |||||
| 10 | RESET INLET FRAME & GRATE w/ NJDEP J-ECO | 20 | EACH | ||
| Write Unit Price and Item Total : | |||||
| 11 | CONCRETE SIDEWALK, 4" thick, w/ Slate disposal | 2300 | S.Y. | ||
| Write Unit Price and Item Total : | |||||
| 12 | REINF. CONCRETE D/W APRON, 6" thick | 550 | S.Y. | ||
| Write Unit Price and Item Total : | |||||
| 13 | DRIVEWAY RESTORATION, MIX I-5 | 150 | S.Y. | ||
| Write Unit Price and Item Total : | |||||
| 14 | GRANITE BLOCK CURB, Conc Curb/Gutter disposal | 5,000 | L.F. | ||
| Write Unit Price and Item Total : | |||||
| 15 | SAW CUTS, 4" DEPTH | 5,200 | L.F. | ||
| Write Unit Price and Item Total : | |||||
| 16 | UNCLASSIFIED ROADWAY EXCAVATION | 300 | C.Y. | ||
| Write Unit Price and Item Total : | |||||
| 17 | 15" DIA. REINFORCED CONCRETE PIPE, CL 5 | 60 | L.F. | ||
| Write Unit Price and Item Total : | |||||
| 18 | DRAINAGE MANHOLE - DOGHOUSE | 1 | EACH | ||
| Write Unit Price and Item Total : | |||||
| 19 | DRAINAGE INLET - TYPE B (WHERE DIRECTED) | 2 | EACH | ||
| Write Unit Price and Item Total : | |||||
| 20 | SELECT BACKFILL | 300 | C.Y. | ||
| Write Unit Price and Item Total : | |||||
| 21 | UNIT BLOCK RETAINING WALL (2' H AS NEEDED) | 1,200 | L.F. | ||
| Write Unit Price and Item Total : | |||||
| 22 | TRAFFIC STRIPING 12" STOP BAR | 80 | L.F. | ||
| Write Unit Price and Item Total : | |||||
| 23 | TRAFFIC STRIPING 6" SINGLE SHOULDER BIKEWAY | 5250 | L.F. | ||
| Write Unit Price and Item Total : | |||||
| 24 | TRAFFIC STRIPING 4" DOUBLE CENTERLINE | 2300 | L.F. | ||
| Write Unit Price and Item Total : | |||||
| 25 | TRAFFIC STRIPING 6 FT X-WALKS w/ DIAGONAL | 200 | L.F. | ||
| Write Unit Price and Item Total : | |||||
| 26 | BIKE ROUTE STENCILING | 12 | L.F. | ||
| Write Unit Price and Item Total : | |||||
| 27 | TRAFFIC SIGNAGE (MUTCD 24") | 6 | EACH | ||
| Write Unit Price and Item Total : | |||||
| 28 | TREE REMOVAL, OVER 12" TO 24" DIA. | 1 | UNIT | ||
| Write Unit Price and Item Total : | |||||
| 29 | TREE REMOVAL, OVER 24" TO 36" DIA. | 4 | UNIT | ||
| Write Unit Price and Item Total : | |||||
| 30 | MAINT. & PROTECTION OF TRAFFIC (MUTCD) | 6 | EACH | ||
| Write Unit Price and Item Total : | |||||
| 31 | CONSTRUCTION SIGNAGE (MUTCD) | 6 | EACH | ||
| Write Unit Price and Item Total : | |||||
| 32 | SOIL EROSION & SEDIMENT CONTROL PLAN | 100% | L.S. | ||
| Write Unit Price and Item Total : | |||||
| 33 | LANDSCAPE RESTORATION - 5600 SY | 100% | L.S. | ||
| Write Unit Price and Item Total : | |||||
| 32 | MISC. ITEMS (Identify) | QTY. | EACH | ||
| Write Unit Price and Item Total : | |||||
| WRITE TOTAL LUMP SUM PRICE FOR GREEN AVE RECONSTRUCTION | |||||