M  A  D  I  S  O  N    P  U  B  L  I  C    S  A  F  E  T  Y    C  O  M  P  L  E  X

 
PHOTOS COURTESY OF FIREFIGHTER  DANIEL PHILLIPS AND CAPTAIN LOUIE DeROSA  ~ (PHOTOS ADDED WEEKLY)

MARCH 15, 2006 (ABOVE)
The foundation is shown with water proofing material at the base of the foundation.

MARCH 15, 2006 (LEFT)
A concrete pumping truck was utilized to pump concrete into the second section of the foundation. 

     
MARCH 24, 2006 (ABOVE & RIGHT)
Workers are shown utilizing a concrete pumping truck to deliver concrete for the basement floor.
     

APRIL 4, 2006 (ABOVE)
Madison Electric Utility lineman, David Artiglere is shown working on relocating high voltage power lines.

APRIL 7, 2006 (ABOVE)
A wooden stairway is constructed to provide workers easy access to the basement.

APRIL 10, 2006 (ABOVE)
Masons work on completing the footings for the front of the fire apparatus room.

APRIL 17, 2006 (ABOVE)
A worker is shown utilizing a piece of equipment to compact soil around the outer walls.



APRIL 17, 2006 (ABOVE)
Masonry footings are approximately 80% complete.

 


MAY 1, 2006 (ABOVE)
Eight flatbed tractor trailer arrive in Madison with the Steel.
The steel is off loaded with the crane shown above.


MAY 1, 2006 (ABOVE)
The first steel I-beams are set into place.

 

 