Construction has commenced at the Southeast corner of Kings Road and Prospect Street, for the new home of Fire & Police Facility for the Borough of Madison. The result of a fourteen year study, the new Fire & Police Facility will replace the current quarters at the Hartley Dodge Memorial Building, where the Police and Fire Departments have been quartered since 1935. The Hartley Dodge Memorial Building will undergo major renovation to accommodate the borough court and other municipal offices. The new facility was designed by Holt Morgan Russell of Princeton New Jersey and will cost approximately $11 million dollars. The new building will give the Police and Fire Department over 37,000 square feet of space compared to 9,000 at the Hartley Dodge Memorial Building. The construction contract was awarded to Eastern Builders of Hazlet New Jersey. Construction is expected to last 16 months. A progress report will be made available on this website as construction moves forward. |
||||
|
|
|||||
|
DECEMBER 7, 2005 (RIGHT) About 60 people braved the frigid December cold and attended the ground breaking ceremony for the new Fire & Police Facility Wednesday morning. Pictured left to right are Captain DeRosa, Chief Chirico, Chief Atchison, Captain Trevena and Captain Nunn take part in breaking ground. |
![]() |
||||
DECEMBER 20, 2005 (ABOVE) Construction crews from Eastern Builders begin preliminary excavation work.
|
|
||||
![]() JANUARY 10, 2006 (ABOVE) Sergeant Brightly (Left) and Captain DeRosa (Right) look over excavation work. |
|||||
![]() JANUARY 8, 2006 (ABOVE) During the excavation process a concrete wall, which was a former coal bin, was discovered.
|
JANUARY 26, 2006 (ABOVE) |
||||
|
|
|||||
|
|
|
||||
|
FEBRUARY 6, 2006 (ABOVE) Forms are being erected on the Northwest Corner of the construction project. (ABOVE / LEFT) The Hartley Dodge Memorial Building can be seen in the background.
|
|||||
|
FEBRUARY 10, 2006 (ABOVE) More of the footings are being poured. The footings to the South (The right side of the photo) is the final outer wall of the basement.
|
|||||
|
FEBRUARY 14, 2006 (ABOVE) Despite over sixteen inches of snow workers clear a path leading to the bottom of the forms so work can progress.
|
FEBRUARY 22, 2006 (ABOVE) A view of the inside of the forms can be seen prior to the pouring of concrete. |
||||
|
|
|||||
|
FEBRUARY 24 (ABOVE) A concrete pumping truck was utilized to pour the first section of the forms.
|
|||||
|
FEBRUARY 24 (ABOVE) The concrete pumping trucks 140' boom is in place to start sending concrete into the forms.
|
FEBRUARY 24, 2006 (ABOVE) Workers start to fill the forms with concrete at the Kings Road and Prospect Street Corner. A freight train can also be seen in the background traveling eastbound on the Morris Essex Line.
|
||||
|
FEBRUARY 24, 2006 (ABOVE) Workers continue to fill the forms utilizing the boom from the concrete pumping truck. |
|||||
|